Major Tenders announced

 
1. Expansion, development , improvement and replacement of the Northern Cooling water
Station in Shuaiba Industrial Area.

Client: Public Authority for Industry
Closing date: 18.01.2004
Official Gazette No.640

The following companies are qualified to participate in this tender:
  
   1. Ebara, Japan
   2. Weir Pump Limited, England
   3. KSB AktiengesellschafT, Germany
   4. Hyundai Heavy Industries Co, Korea
   5. A- C Custom Pump , USA
   6. Flowserrve B V. Hengelo stork(Formerly), USA- Holand
   7. Torishima and Doosan , Japan Korea
   8. T.M.P.S. Corporation Termomeccanica Pompe, Italy
   9. Alstom Fluid Et Micaniqe , France
   10. Kubota Corporation , Japan
   11. Sulzer Pumps co, USA
   12. Johnston Pump Co, USA
   13. Cornel Pump Co, USA
   14. Hyosung Ebara Co, LTD, Korea
 
2. Supply, installation and commissioning of local network and the associated devices in addition to the computers, printers accessories, software and commissioning systems relating thereto and connecting thereof with special international network in the corporation inside and outside the State of Kuwait as well as carrying out the free maintenance thereto.
 
Client: Kuwait Airways Corporation
Closing Date: 09.12.2004
Official Gazette No. 640
 
3. Construction, Completion, Commissioning and maintenance of theatre building, display hall and building of administration and substation in the building No. 31KH and the substation.
 
Client: Kuwait University
Closing Date: 09.12.2004
Official Gazette No. 641

11 local companies are qualified to participate in this tender.
 

Pre- Qualification Announced


AROMATICS PLANT

   The Petrochemical Industries Limited (PIC) is in the process of qualifying international contractors for a grass root Aromatics Complex to be erected and constructed at the Shuaiba Industrial Area in Kuwait, based on processing 2.5 Million ton per annum to full range Naphtha feed for the production of Paraxylene and Benzene. The start up of the Aromatics Plant is scheduled for 2007.
   As a pre-requisite of this qualification, only those international engineering, procurement and contracting companies that have carried out EPC services in lump sum turnkey basis for at least one single successfully commissioned grass root project outside their country of origin over the past 10 years, having the same characteristics as Refineries and/or Petrochemical Plants and having a total project installed value of not less
than five and hundred million U.S. Dollars (500 Million US $).
   All reputable interests international Contractors are lived their qualification documents based on the pre-qualification inquiry requirements requested by PIC which can be obtained from central Tender Committee State of Kuwait starting as November 2,2003 of for a nominal none refundable fee of Fifty Kuwaiti Dinars (KD 50). The last date for submitting the documents for pre-qualification is January 3,2004.
 

Get Represented in Kuwait

 
    ARABI ENERTECH represents several internationally reputed companies in Kuwait. Being a company in operation for 25 years with good reputation and contacts with all major clients in Kuwait such as Kuwait National Petroleum Company (KNPC), Kuwait Oil Company (KOC), Petrochemical Industries Company (PIC), Ministry of Electricity & Water and various other ministries, Arabi Enertech will be more than pleased to represent any international company of repute and promote their products/services in Kuwait market, provided their products are not represented by us from our other principals.

    If interested, you may please contact us on e-mail: trading@arabienertech.com.

For your thought...

1. I look forward to being older, when what you look like becomes less & less an issue & what you are is the     point.

2. Flexible people never get all bent out of shape.

3. Look it up – you’ll remember it longer.

4. When you help someone up a hill, you get that much closer to the top yourself.

Laughter...the best medicine


1. Patient: “Doctor, I keep feeling there are two of me!”
    Doctor “Very well. I’ll see you one at a time”.

2. “Why are you trying to make a fool out of me?”
    “Not the least- why should I try to change you?

3. Heroine: “After my big death scene they cried all over the house”.
    Producer:“That’s because they knew you weren’t really dead”.

4. Judge: “Are you guilty?”.
    Prisoner: “I haven’t heard the evidence yet?”


<<Previous

P.O.Box 9831 Ahmadi, Kuwait. Ph: +965 3986083 Fax: +965 3986522 email : enertech@arabienertech.com
© Arabi Enertech K.S.C - Kuwait 2005